Operation of pressure test of reactor
2023-08-24
Safety measures shall be taken for the pressure test of the reactor. The reaction gas should be dry, clean air, nitrogen or an inert gas. In the air pressure test, the medium test temperature shall not be lower than room temperature, and the pressure shall slowly rise to 10% of the specified test pressure and not more than 0.05MPa during the test. Hold the pressure for 5 minutes, and then perform an initial leak check on all welded joints and joints. If there is a leak, retest after repair.